Indoor Pool Project

October 23, 2018 – Water Technology Inc, and LCA Architects presented to the Board of Directors and staff about the indoor pool plans. The presentation included various features that the pools can have such as water geysers, water tables, ceiling water features, waterslide  interaction features, etc. WECRD is beginning the ‘Schematic Phase’ of the pool design and with the guidance of LCA and WTI they will be able to finish the details of the plans. This process takes approximately 4-6 weeks to complete. These will be the plans that move forward to the construction phase. WECRD has decided to hire a Construction Manager/General Contractor for the construction process, the Request for Qualifications will be advertised October 31st and November 7th with them due by December 6, 2018. 

WTI Presentation 10.23.18

RFQ for Construction Manager / General Contractor

____________________________________________________________________________________________________________________________________________

October 3, 2018-  Meeting with LCA Architects – The board signed the contract with LCA Architects. Our next step is to schedule a meeting with the pool consultant, engineers, and architects to work out the final details on the pool design. A ‘request for qualifications’ (RFQ) will be sent to publication once the board approves the type of RFQ they want to consider, (Lowest Bid vs. General Contractor/Construction Manager). This will be voted on at the next WECRD board meeting. The most exciting part of the meeting was when LCA said they are hopeful that construction can begin in Spring 2019. 

_____________________________________________________________________________________________________________________________________________

September 5, 2018 – The WECRD Board approved LCA Architects proposal to be the architect firm for the indoor pool project. Next step, LCA will draft a contract of services for the board to approve. 

_____________________________________________________________________________________________________________________________________________

August 2, 2018 – We are Requesting Proposals for Architectural and Engineering services in regard to a project to build an Indoor Pool Facility in Mountain Home, Idaho. Proposals are due back August 24, 2018. 

Project Particulars:
We envision a multi-purpose and multi-generational indoor pool facility that is approximately 22,000 sq. ft., complete with a six lane competitive lap pool, a leisure pool which includes a zero-depth entry, lazy river, and general use pool, there is also a whirlpool/spa, waterslide, and splash pad area. Also included in this facility will be men and women locker rooms, multi-purpose community rooms, office space and storage.

The WECRD desires that the new indoor pool facility be planned, designed and built in a collaborative manner with community input and task force oversight. We wish to explore and implement opportunities for this to be a state-of-the art facility, incorporating a sprung building design, and sustainability and energy conservation concepts, if affordable on a life-cycle cost basis.

The WECRD requests demonstrated competence to: work within a specific design/construction budget, maximize the use of space for an indoor pool facility while providing optimal visual appeal.  Additional discussion regarding the specifics and location of the facility, budgetary parameters, as well as the project timeline, will be available at the interviews.

_____________________________________________________________________________________________________________________________________________

July 18, 2018  – Presentation of plans from LCA Architects
Pool design of the inside
Pool design of the outside
Indoor Pool 2018 Projected Budget

_____________________________________________________________________________________________________________________________________________

June 25, 2018 – Meeting with LCA Architects and WTI, Inc.

They provided us with designs and costs associated with building an indoor pool. The different options would be a dome/bubble enclosure, Sprung Building, Metal/pre-fabricated building, and/or conventional build.  With the funds WECRD has currently, the Sprung Building is our first option with a potential for a conventional build for office spaces, locker rooms, etc. LCA Architects will be at the July 18th Special Board Meeting with their design(s) to show us.

Sprung designs high performance tensioned membrane structures that take only days to customize and weeks to build. Our innovative building solutions are engineered for total design flexibility, all-weather performance and strength, long term quality and cost-effectiveness. (Sprung.com)”

Here are some pictures of Sprung Pools:

         

Mountain Home ID WECRD Aquatic Program Presentation 2018-05-21[4080]

Water Technology Inc. provided us with this great presentation of all the various pool options out there. Our goal is to provide the Mountain Home community with a multi-purpose and multi-generational pool facility. We will keep you informed on our progress. Contact WECRD if you have any questions.