Phase III

On June 22, 2021 the Board approved the bids to move forward with Phase III. The cost is $3.4 million. Wright Brothers is coordinating the construction timeline and this phase will take approximately 8 months. Stay tuned for progress reports and pictures of our progress! 

This phase will consist of all work to the top of finished floor. Work includes the following:

  • Excavation/Earthwork
  • Wet/Dry utilities (existing utilities already brought into the pad site)
  • Concrete
  • Pool Systems
  • Electrical
  • Plumbing