18th St. Construction and WECRD Updates
The City has begun construction on 18th St. and as they worked their way to our property it has created some hurdles. WECRD needs to get the gas lines, water lines, and sewer lines into the ground before the road is capped and finished. The City also began digging a retention pond on the property that was not in the most recent agreed upon spot. This made WECRD and their design team scramble to change the site plan to fit the retention pond where it was started to help save the City money. Thankfully, Lee Pierce has been able to work diligently with the City, LCA, The Land Group, and Wright Brothers, on this issue to resolve it. Once 18th street is done, the WECRD plans on breaking ground with the construction phase of the indoor pool facility in June.