Pool Update – November 14, 2018

WECRD board, staff and the Foundation met with LCA and WTI on Wednesday November 14th to discuss the schematic pool design. LCA added family locker rooms, an upper mezzanine for storage, and more office space to the previous plan. They also redesigned the layout of the rooms and made the flow of the building better. WTI added details to the pools and presented three concepts for the leisure pool.  After discussion on the plans the board agreed one design had a better layout then the others. WTI and LCA will continue refining the plans to be ready for the site plan. The site plan will be discussed on December 12th at the WECRD building.